Where power, equipment and schedule collide.

We work on the physical infrastructure behind digital capacity, reliable power and public services. The common thread is long-lead electrical equipment and a schedule that cannot wait for it.

TransformersLead times 60–120+ weeks
MV switchgearLead times 40–80 weeks
Gas turbinesLead times 100+ weeks
Mobile generationWeeks, if sourced early

Lead-time ranges are indicative of current market conditions and vary by rating, manufacturer and region. We confirm against live supplier quotes for every requirement.

DATA CENTERS

Power before compute.

A data center is a power project with servers at the end of it. Generation, utility interconnection, transformers and switchgear decide the ready-for-service date more than the building does. We source that equipment, track the long-lead items and coordinate the interfaces with the EPC and the utility.

  • On-site and bridging generation sourcing
  • Transformer and switchgear procurement
  • Long-lead tracking against RFS date
  • Utility and EPC interface coordination
  • Owner-side PM for multi-phase campuses
  • Vendor documentation and submittal control

Discuss a data center requirement

ENERGY & UTILITIES

Generation and substation equipment, delivered on plan.

Utilities, co-ops and independent power producers face the same equipment queue as everyone else, with regulatory reporting on top. We run sourcing and project controls so the procurement record is clean and the schedule is defensible.

  • Generation equipment sourcing
  • Substation and distribution equipment coordination
  • Supplier documentation and QA packages
  • Schedule, readiness and milestone tracking
  • Program reporting for boards and regulators

Discuss an energy requirement

INDUSTRIAL & FACILITIES

Expansion and replacement without the downtime.

Manufacturing, logistics and process facilities adding load or replacing aging electrical gear need the new equipment to arrive before the outage window, not after. We scope the requirement, source the equipment and coordinate the cutover.

  • Facility power requirement definition
  • Replacement and expansion sourcing
  • Procurement workstream management
  • Construction and operational handover

Discuss a facility requirement

PUBLIC SECTOR

Program management and procurement support for agencies.

Federal, state and local agencies buy the same way we work: defined scope, documented process, regular reporting. We support agency programs as a prime or subcontractor, for facilities, energy-resilience and IT programs.

  • Program and project management support
  • Acquisition and procurement support
  • IT and SaaS implementation PMO support
  • Facility and energy resilience equipment sourcing
  • Independent verification and reporting

Government contracting page

Equipment sourcing focus

Start with the requirement. Build around the project.

Generation

Gas turbines, reciprocating engine gensets, mobile and rental generation, fuel systems and supporting packages.

Electrical infrastructure

Transformers, medium- and low-voltage switchgear, UPS and battery energy storage, protection and distribution equipment.

Project interfaces

Fuel, electrical, foundation, delivery and commissioning requirements coordinated with the responsible technical teams.

Next step

Tell us the rating, the location and the date you need it.